Overview
-
Rail
Project type -
$15.5 million
Total budget -
Complete
Project phase -
Public Transport Authority
Lead agency -
35
Jobs supported
The upgrade of Nowergup Depot will increase maintenance capacity ensuring the reliable and efficient operation of Transperth services.
Located east of Ridgewood between Clarkson and Butler stations, the depot is used to stow and service railcars operating on the Mandurah and Joondalup lines.
The project included construction of a new maintenance building including 370m of wired rail track, 200m of unwired rail track to store track maintenance machines, and a new 800m train drivers footpath.
Benefits
Gallery
Project map
This map shows an aerial view of the project location.